13 men dig a trench, 9whole 2/7m long in 1 day . how many men should be employed for digging a trench, 15 m long in 1 day​

Answers

Answered by mraggarwal02
0

Answer:

21

Step-by-step explanation:

total men needed = 13 x 7/65 x 15

=21

Answered by nareshsingha6296
21

Answer:

21

Step-by-step explanation:

this is the correct answer ok