14. A can do a work in p days and B can do it in 2p days. They started to do the work together and after some days A left the work unfinished. B completed the rest of the work in r days. In how many days was the work finished?
Answers
Answer:
let x be the days when both A & B worked together.
x (1/p+1/2p)+r(1/2p)=1
(2x+x+r)/2p=1
3x+r=2p
r=2p/x
total days=x+r=x+(2p/x)=(x^2+2p)/
if you didnt understand above then se below
A can do a work in p days and B can do it in 2p days. They started to do the work together and after some days A left the work unfinished. B completed the rest of the work in r days. In how many days was the work finished?
let x be the days when both A & B worked together.
x (1/p+1/2p)+r(1/2p)=1
(2x+x+r)/2p=1
3x+r=2p
r=2p/x
total days=x+r=x+(2p/x)=(x^2+2p)/x
A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in how many days?
A & B do work in 12 days, B & C do the same work in 16 days, A & B finish work in 6 days, and A & C will do this in approximately how many days?
A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 15 days, A finished the remaining work. In how many days can A alone finish the job?
A and B can together finish a work in 50 days. They worked together for 20 days and then B left. After another 30 days, A finished the remaining work. In how many days can A alone finish the job?
A can do a work in 14 days and B can do the same in 35 days. Starting with A he is assisted by B on alternate days. In how many days will the work be finished?
The job of work is p A-mandays
and is 2p B-mandays
Therefore 2 B-mandays = 1 A-manday
A and B start work together. After x days A leaves
At that stage
x A-mandays and x B-mandays
of work have been completed. This equals
2x B-mandays + x B-mandays = 3x B-mandays. of work so far.
B finishes the work in r days, i.e. r B-mandays
Therefore time for the whole job in B-mandays is (3x + r)
Therefore (3x + r) = 2p
Thus x = (2p – r)/3
Time to complete the whole job is (x + r) man days
= (2p – r)/3 + r days = (2/3) (p + r)
= Two thirds of (p + r) days.
Step-by-step explanation:
if you understand then only mark as brainlist
and follow