14. Ajay can do a piece of work in 25 days and Sanjay can finish it
in 20 days. They work together for 5 days and then Ajay goes away
In how many days will Sanjay finish the remaining work?
(a) 11 days
(b) 12 days
(c) 14 days
(d) None of these
Answers
Answered by
0
Answer:
Step-by-step explanation:
Ajay' s 1 days work = 1/25
Similarly, sanjay's 1 days work = 1/20
Ajays and Sanjay 's together 1 day's work
= (1/25) + (1/20) = (4 + 5)/100 = 9/100
Their 5 day's work together
= 5 x 1 day's work
= 5 x (9/100) = 45/100
Remaining work = 1 - (5/100) = 55/100
Now, this remaining work is done by Sanjay.
Let Sanjay takes N days to complete it.
Then, (1/20) x N = 55/100
⇒ N = (55 x 20)/100
∴ N = 11 days
So, remaining work is done in 11 days by Sanjay.
thank you
Answered by
1
11 days.
If it helps, kindly mark me the brainliest.
:)
Happy studying!