Math, asked by naruto982830, 3 months ago

14. If 12 men and 16 boys can do a piece of work
in 5 days and, 13 men and 24 boys can do it
in 4 days, how long will 7 men and 10 boys take
to do it ?​

Answers

Answered by clair225
2

Answer :

here u go

Step-by-step explanation:

you will have to find the number of man-days and boy-days required to do the job and equate it.

5(12M+ 16B) = 4(13M + 24B) since the same work is done they will be equal

60M + 80B = 52M + 96B

8M = 16B or M = 2B substitute 2B = M and you will get the total man-days required to do the job and it is

5( 12M + 8M) = 100 man-days

so,

x(7M+10B) = 100M

x(7M+5M)=100M

solving this x =25/3 days so 7 men and 10 boys will have to work for 25/3 days to complete the job

Similar questions