14. If 12 men and 16 boys can do a piece of work
in 5 days and, 13 men and 24 boys can do it
in 4 days, how long will 7 men and 10 boys take
to do it ?
Answers
Answered by
1
Answer:
5(12 M + 16 B) = 4(13 M + 24 B)
60M + 80B = 52M + 96B
That gives, 8M = 16B, which is , 1M=2B
Now, 12 M + 16B can do work in 5 days.
So, 12 M + 8 M can do work in 5 days.
So, 20M can do work in 5 days.
Now, 7M + 10B = 7M + 5M = 12 M
Hence, if 20M can do work in 5 days, 12M can do work in (20*5)/12 = 8.33 days.
Similar questions