14 If 12 persons can complete a piece of work in 20 days, how many days will it take 15 persons to complete the
work?
Answers
Let us suppose 15 men finish a work in 'x’ days Then 20 : x = 5 : 4
x= 16 i.e required number of days.
Or
Men(M1) * Days(D1) = Men(M2) * Days(D2)
Here, M1= 12 , M2 = 15 and D1= 20 and D2 = ? Suppose x
Now , from this formula
12 * 20 = 15 * x
240 = 15x
x= 240/15
x= 16
Answer:
16 days
Step-by-step explanation:
Work’ is directly proportional to Time 't’( more work, more time) principal
Ratio of numbers of men = 12:15 = 4:5. The ratio of times taken = 5:4. (Here ratio of time was taken not the ratio of days. The ratio of time taken is obtained by interchanging values of 1 st men and 2 nd men)
Now take the ratio between time and work then you will get answer
Let us suppose 15 men finish a work in 'x’ days Then 20 : x = 5 : 4
x= 16 i.e required number of days.
Or
Men(M1) * Days(D1) = Men(M2) * Days(D2)
Here, M1= 12 , M2 = 15 and D1= 20 and D2 = ? Suppose x
Now , from this formula
12 * 20 = 15 * x
240 = 15x
x= 240/15
x= 16