14 men can complete a piece of work in 3 days 21 women take 9 days to complete the same work .How many days will take for 1 man abd 6 women to complete
Answers
Answer:
18 days
Step-by-step explanation:
4M x 3 = 21W x 9
1M = 4.5W
To Find : 1M + 6W = __ days
1M + 6W = 4.5W + 6W = 10.5W
21 women takes 9 days to complete work
so, 10.5 women takes
= (21 x 9) / 10.5
= 18 days will take for 1 man and 6 women.
Given :
14 men can complete one work in 3 days.
21 women can complete one work in 9 days.
To find:
The number of days to complete one work by one man and six women.
Solution:
We know the formula for time and work,
(M₁ ×D₁ × H₁)/ W₁ = (M₂ × D₂ × H₂)/ W₂ ( formula 1 )
Using this formula,
14 Men × 3 days = 21 women × 9 days ( here, W₁= W₂ = 1)
1 women = (14 Men × 3 days) / (21 × 9)
6 women = ( 6 × 14 Men × 3 days) / (21 × 9)
6 women = (84÷63) men
Now, 1 man + 6 women = 1 man + (84÷63) men = 1 + ( 4 ÷ 3)
= 7/3 men
Using formula 1,
14 Men × 3 days = 7/3 men × D days ( Since W₁= W₂ = 1)
D days = 126 ÷ 7 = 18
Hence, the total number of days taken by 1 man and 6 women = 18 days