14 men can do a piece of work in 11 days working 8 hours a day.in how many days will 22 men finish the same work working 7 hours a day
.
.
.
.. . . . . EMERARUDO HADO (EMERALD HADO)
AGE 15
INDOJAPANESE
IM FROM JAPAN NOW IN INDIA
I'm ARMY, OTAKU, ETC.
Attachments:
Answers
Answered by
2
Answer:
Explanation:
no. of men available to finish the work (W) =22
Each man can work for 7 hrs let’s say X days.
So, each man worked for 7X hrs.
Amount of total time is same for above case = 1232hrs
1232 = 7X * 22
Therefore, X is 8.