14 men can do a piece of work in 11 days working 8 hours a day.in how many days will 22 men finish the same work working 7 hours a day​
.
.
.
.. . . . . EMERARUDO HADO (EMERALD HADO)
AGE 15
INDOJAPANESE
IM FROM JAPAN NOW IN INDIA
I'm ARMY, OTAKU, ETC.​

Attachments:

Answers

Answered by dkaivalya83
2

Answer:

Explanation:

no. of men available to finish the work (W) =22

Each man can work for 7 hrs let’s say X days.

So, each man worked for 7X hrs.

Amount of total time is same for above case = 1232hrs

1232 = 7X * 22

Therefore, X is 8.