14 men can do a piece of work in 11 days working 8 hours a day.in how many days will 22 men finish the same work working 7 hours a day​​

Answers

Answered by Resham1343
2

Answer:

8 days

Explanation:

Total no. of hours required by 14 men to do work = (11days*(8hrs/day) = 88 hours

Total no. of hours required by 1 man to do work = (88*14) hours

Total no. of hours required by 22 men to do work = (88*14)/22 = 56 hours

22 men work 7 hours each day, therefore,

No. of days required by 22 men to do work

= 56/7 = 8 days