14 men can do a work in 18 days ,15 women can do a work in 24 days. If 14 men work for first three days and 10 women work after that for three days find the part of work left after that?
Answers
Answer:
Explanation:
14 men can do the work in 18 days, therefore
1 men can do the work in 1814 days
15 women can do the work in 24 days, therefore
1 woman can do the work in 2415 days
Therefore total work completed by them becomes
Question-
14 men can do a piece of work in 18 days, 15 women can do a piece of work in 24 days. If 14 men work for the first three days and 10 women work after that for three days find the part of work left after that?
Answer-
Let us assume that the work done by every man is equal and the work done by every woman is equal.
14 men can do a piece of work = 18 days
14 men's work done in one day = 1/18 of the work
15 women can do a piece of work = 24 days
15 women's work done in one day = 1/24
1 women's work done in one day = 1/(24 × 15)
10 women's work done in one day = 10/(24 × 15)
Work done by 14 men in 3 days = 3/18
= 1/6 of the work
Work done by 10 women in 2 days = (10 × 3)/(24 × 15)
= (2)/(24)
= 1/12 of the work
Total work done = 1/6 + 1/12 = (2 + 1)/12 = 3/12 = 1/4 of the work
Remaining work = 1 - 1/4 = 3/4