14 men can plough a field in 27 days how many men will be needed to plough it in 63 days
Answers
Answered by
0
Answer:
Step-by-step explanation:
Here you go...
Let the no. Of required men be x so
14:x=27:63
It's an inverse proportion so
Or,14/x=63/27
Or,x=14*27/63
So...x=6..
And the no. Of needed men is 6.
Hope this will help you...
Answered by
3
Step-by-step explanation:
Here is your answer. If this is helpful to you then pls mark it as brainliest