14 women can do a piece of work in 48 days. If 6 of the women deny to work, then how many days are required to complete the work?

Answers

Answered by aditilande9
20
14 women do work in 48 days
6 women deny so 8 women left (14-6=8)
so now let the days be x
14×48=8×x
x=14×48/8
x=84
84 days
Answered by TooFree
5

Find the number of days needed for 1 woman to finish the work:

14 women = 48 days

1 woman = 48 x 14 = 672 days


Find the number of women at work:

Number of women = 14 - 6 = 8


Find the number of days needed for 8 woman to finish the work:

1 woman = 672 days

8 women = 672 ÷ 8 = 84 days



Answer: They will need 84 days