14 workers in 5 days make 1400 toys. One day
after the work starts 14 more workers join. In
how many days the rest of the work will be
completed?
(a)2
(b)3
(c) 2.5
(d)3.5
Answers
Answered by
0
Answer:
C is the best way question
Answered by
0
Answer:
the answer is 2.5 accorfing to me