Math, asked by shivdesh3037, 10 months ago

14 workers in 5 days make 1400 toys. One day
after the work starts 14 more workers join. In
how many days the rest of the work will be
completed?
(a)2
(b)3
(c) 2.5
(d)3.5​

Answers

Answered by Ahinush
0

Answer:

C is the best way question

Answered by Kaash2008
0

Answer:

the answer is 2.5 accorfing to me