14 workers produce 1400 toys in 5 days. After one day's work
was over, 14 more workers joined them. In how many days can
they complete the remaining work?
mdanas71:
shahruk
Answers
Answered by
2
in 5 days 14 workers make = 1400 toys
when 14 workers join them then
total workers= 28
so work done by 28 workers in 2.5 fays