1400 Labourers can finish the construction of a school in 80 Days how many more labours needed to construct the school in 20days
Answers
Answered by
7
Answer:
1400 labours for 80 days
for 20 labours how much
soln:
80/20=4
1400*4=5600
so
5600 - 1400 = 4200