15). 12 men complete a work in 5 days. How many men are required to complete same work in 6 days?
Answers
Answered by
1
Answer:
14 or 15 men
Step-by-step explanation:
Answered by
0
Answer:
the work is already done by the 12 men. just kidding
Step-by-step explanation:
5 days = 12 men
1 day= 12×5=60 men
6 days= 60/6=10 men required