15
7. The rates of working of A and B are in the ratio 3:4. The number of days taken by them to
finish the work are in the ratio
(a) 3:4
(b) 9:16
(c) 4:3
(d) 16:9
Answers
Answered by
18
We know that the number days taken to work is the reciprocal of the rate of the work i.e they are inversely proportional.
So, we calculate the work done by A=1/3
And the work done by B = 1/4
∴ Ratio of the work done = 1/3 : 1/4 i.e. 4:3