15. A can do a certain job in 12 days. B is 60% more efficient than A. Find the number of days taken
by B to finish the job
16. A is twice as good a workman as B and together they finish a piece of work in 14 days. In how
many days can A alone do it?
Answers
Answered by
2
Step-by-step explanation:
15) Since B is 60% more efficient the rate of B is 1.6 x 1/12 = 1.6/12 = 16/120 = 2/15. Since time is inverse of rate, B can complete the job in 15/2 = 7.5 days. b2bt wrote: A can complete a certain job in 12 days. B is 60% more efficient than A.
16). Together they complete the work in 18 days
So, in one day they complete 1/18 work.
Since A is twice good as B
So A's workdone in one day= 2x
& B's workdone in one day= x
So, 2x + x = 1/18
3x = 1/18
X = 1/54
So, B's workdone in oneday= 1/54
& A's workdone in one day= 1/27
So, A alone will take 27 days to complete a piece of work
Ans: 27 days