15. A can do a plece of work in 10 days and B in 15 days. How long will they take to finish it working together?
Answers
Answered by
60
Work done by A in 1 day=1/10
Work done by B in 1 day=1/15
Work done by A and B=1/10+1/15
Work done by A and B=25/250
working together they will complete the work in 150/25=6 days
Answered by
2
Answer:
Working together, they can finish the work in 2 days.