15 boys can do a piece of woek in 18 days ,how long will 20 boys do it
Anonymous:
___k off
Answers
Answered by
0
Work Done by one boy = 15 / 18 days
Work done by 20 boys = 15 * 20 / 18
= 50/3 = 16* 2/3 days