Math, asked by amatyaaashmi123, 4 months ago

15 labourers were employed to
build a wall in 28 days
How
many more Labourers should be
employed
to finish the construction
in 21 days?​

Answers

Answered by sumit456456
7

Answer:

28 days for 15 workers

1 day will require 15/28 workers

21 day will require (15/28)x21 = 45/4

Answered by ysaloni224
1

Answer:

hlo iwant points and I will tell uh later