Math, asked by amatyaaashmi123, 3 months ago

15 laboures were employed Zo
build a wall in 28 days .How
many more
Laboures should be
employed to finish the construction
in 21 days?

Answers

Answered by khushibabu21
1

Step-by-step explanation:

15 \: labours \: can \: build \: a \: wall \: in \: 28days \\ 1 \: labour \: can \: build \: a \: wall \: in \: 28 \times 15 = 420 \: days \\ in \: 21 \: days \: the \: wall \: build \: by  \frac{420}{21}  = 20 \: labours