Math, asked by divithswarup6413, 1 year ago

15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days. how many days will 10 men and 10 boys together take to complete the same work?

Answers

Answered by pravinsir
2
15 men --------- 10 days

1 man --------- 150 days

10 men --------- 15 days

also ,

20 boys --------- 15 days

1 boy --------- 300 days

10 boys --------- 30 days


now 10 men takes 15 days

so in one day they complete 1/15 of work

10 boys takes 30 days

so in one day they complete 1/30 of work

both together completes the work in one day = 1/15 + 1/30

= 45 / 15 ×30

= 1/10 of work

so together they fulfil the work in 10 days