15 men can complete a work in 12 days they start work together. In how many days the total work will be finished when
(1) After 4 days 5 more men join the work.
(2) After 4 days 5 men left the work.
Answers
Answered by
0
Answer:
15 men can do the work in 12days.
After 4 days remains work of 8days.
If 15 men can do that in (12-4) 8 days
Then 1 man can do in 15x8= 120 days. After 4days 5 more men joins the work
So total (15+5) 20 men can do the rest work (120÷20)= 6 days. Ans.