Math, asked by preethiravii, 1 day ago

15 men can complete a work in 8 days while 10 women can complete the same work in 20 days. 7 men starts working and after 12 days they are replaced by 10 women. Find time taken by 10 women to complete the remaining work.

Answers

Answered by limon9632
0

Answer:

6 days

Step-by-step explanation:

Let the complete work is 1.

15 men do that in 8 days.

1 men do 1/120 part of work in 1 day

7 men do 7/120 part of work in 1 days

7 men do 84/120 part of work in 12 days

remaining work is (1- 84/120)=36/120=6/20

again 10 women do that in 10 days

10 women do 1/20 part of work in 1 day.

1/20 part of work done in 1 day

1 part of work done in 1*20=20 days

so, 6/20 part of work done in 6/20*20=6 days.

so answer is 6 days

Answered by Abhijeet1589
0

The answer is 6 days.

GIVEN

15 men can complete a work in 8 days while 10 women can complete the same work in 20 days. 7 men starts working and after 12 days they are replaced by 10 women.

TO FIND

Time taken by 10 women to complete the remaining work.

SOLUTION

We can simply solve the above problem as follows;

It is given that,

15 men can complete work in 8 days.

So,

Number of days taken by 1 man to complete the work = 15 × 8 = 120 days

And,

10 women can do work in 20 days.

So,

Number of days taken by 1 woman = 20 × 10 = 200 days

Taking the LCM of the number of days taken by man and woman

LCM of 120 and 200 = 600

Efficiency of Man = 600/120 = 5

Efficiency of woman = 600/200 = 3

Let the time taken by 10 women to do the remaining work = t days

Amount of work done by 7 men in 12 days = (7×5) × 12 unit

Amount of work done by 10 women in t time = (10×3)×t

Total work = 600 units

So,

(7×5 × 12) + (10×3×t) = 600

420 + 30t = 600

30t = 600-420

30t = 180

t = 180/30

t = 6 days

Hence, The answer is 6 days.

#Spj2

Similar questions