Math, asked by ukroy2015, 3 days ago

15 MEN CAN COMPLETE THE CONSTRUCTION OF WALL IN 12 DAYS. IN HOW MANY DAYS CAN 18 MEN CAN COMPLETE THE JOB ?

Answers

Answered by manreetkaur99
0

Answer

15 men = 12 days

15 :18::12:x

15×18::12

270/12

=22.5

x=22.5

means in 22.5 days 18 men can finish their job

2nd method

15 men = 12 day

1 men = 15÷12

=1.25

18 men =1.25×18

=22.5

Attachments:
Similar questions