15 men can construct a road in 12 days. How many days are required to construct the same road in 9 days? (Assume each person works at the same rate.)
ans this as fast as possible..pls
Answers
Answered by
0
solved below,
Step-by-step explanation:
given is,
15men can do the work in= 12 days
work done in one day= 15/12 men
work done in 9 days= 45/4
45/4 men can do the work in9 days.