15 men can din a pit in 8 days-how many men can din it in 6 days?
Answers
Answered by
0
12 men take 6 days to complete a piece of work.
1 man takes (12 x 6) = 72 days to complete a piece of work.
18 men take (72/18) = 4 days to complete a piece of work.
Mark as branlist
I had given first answer
1 man takes (12 x 6) = 72 days to complete a piece of work.
18 men take (72/18) = 4 days to complete a piece of work.
Mark as branlist
I had given first answer
Answered by
1
this is the answer please mark it as brainliest