Math, asked by wwwsoundtrackvrx, 3 months ago

15 men can do a piece of work in 12 days. Find the number of men required, if the same work is to be completed in 6 days. explain

Answers

Answered by keesarivinay19
0

Answer:

15×12=X × 6

X=30 men

This is the exact ans

Answered by hiranmayee38
1

Answer:

ATQ

15/6= x/12

X= 15× 12/6= 30

So it will take 30 men to complete the work in 6 days

Step-by-step explanation:

I hope my answer will help you a lot