15 men can do a piece of work in 20 days, in
how many days 25 men finish the same
work?​

Answers

Answered by AtqClasses
0

Answer:

12 Days

Step-by-step explanation:

15 Men x 20 Days = Work ——— (1)

25 Men x No of Days = Work ——— (2)

from equation (1) and (2)

25 Men x No of Days = 15 Men x 20 Days

 No  \: of Days =  \frac{ 15 Men  \times  20 Days }{25 Men}

No of Days = 3 x 4 = 12