15 men can do a piece of work in 20 days ln how many days can 25 men finish the same work
Answers
Answered by
1
5 days
hope it helps you...
Answered by
2
Step-by-step explanation:
Using direct proportion method
15 men do work in 20 days
Therefore 25 men do work in =15*20/25=12