15 men can do a work in 210 days for every 10 days 10 men will leave the work then in how many days the work will be completed?
Answers
Answer:
Step-by-step explanation:
15 men do 1 work in 210 days
So 15 men will do 1/210th work in 1 day
So "1 man will do 1/3150th work in 1 day"<----use this as your main statement
Now lets start , keeping in mind the base statement,
First 10 days there are 15 men working so the work completed will be 1/3150*10 days*15 men=1/21
Next 10 days there are 30 men working so the work completed will be 1/3150*10 days*30 men=2/21
Next 10 days there are 45 men working so the work completed will be 1/3150*10 days*45 men=3/21 (or 1/7)
This will continue as 4/21,5/21 and so on...
If you notice when you reach 6/21 and add all the work, it will be 21/21 = 1 which means the work has completed.
That means the number of days to complete the work would be 10+10+10+10+10+10= 60 days.
So the answer is 60 days!