15 men can finish a piece of work in 8 days. 18 women can finish the same piece of work in 12 days and 16 children can finish it in 20 days 12 women and 8 children started working together and worked for 10 days. if the remaining work need to be finished in 2 days, how many men should be added to the existing number of workers
Answers
15m in 8days , 18w in 12days , 16c in 20days
1m complete wrk in 120days , 1w in 216days , 1c in 320days
12w and 8c complete the work in 360/29 days
So in 10 days they complete 29/36 wrk
Remaining wrk is 7/36
1m complete 1 work in 120days
1m complete 7/36 work in 70/3 days
So x men complete 7/36 work in 2 days
X= 70/6 = 11.66 = 12(approx)
Pls mark it as Brainliest!
Given:
15 Men complete a piece of work in 8 days.
18 Women complete the same work in 12 days.
16 Children complete the same work in 20 days.
12 Women and 8 children started working together and worked for 10 days.
To Find:
The number of men that should be added to the existing number of workers so that the remaining work is finished in 2 days.
Solution:
Let M denotes men, W denotes women and C denotes children.
According to the question, we have
Therefore,
Since 15 men can complete a piece of work in 8 days, therefore,
Total work
Let the number of men that should be added to finish the remaining work in 2 days be .
Now, according to the information given, we have
Dividing both sides by , we get
Hence, 2 more men should be added to the existing number of workers to finish the remaining work in 2 days.