Math, asked by 8152934561kiranmai, 2 months ago


15 men can finish a piece of work in 8 days. 18 women can finish the same piece
of work in 12 days and 16 children can finish it in 20 days 12 women and 8
children started working together and worked for 10 days. If the remaining work
need to be finished in 2 days, how many men should
be added to the existing
number of workers ?
1) 4
2) 2
3) 5
4) 6
5) 3​

Answers

Answered by 24xia3shriyamrastogi
0

5 men work in remaining day c


8152934561kiranmai: only 2 members should add ...plz check ur answer