Math, asked by mayankjha1570, 1 year ago

15 men could finish a piece of work in 210 days. But at the end of 100 days, 15 additional men are employed. In how many more days will the work be complete? A.

Answers

Answered by varnittripathi
20
Therefore,
1 man requires 15 * 210 = 3150 days to complete the same work 
So, in 1 day 1 man complete 1/3150 of the total work 
Thus,
In 100 days 15 men completes (15 * 1/3150 * 100) = 10/21 of the total work 
After 100 days there are 30 men,
They will complete the remaining task i.e. 1 - 10/21 of the total work in 1/30 * 11/21 * 3150 = 55 days.

varnittripathi: please make as branliest answer
Answered by rishika79
2

Step-by-step explanation:

10 day's work by 15 men = 10/210 = 1/21

At the end of every 10 days 15 additional men are employed i.e., for the next 10 days we have 15 + 15 = 30 men

∴ Next 10 day's work by 30 men = 2/21

Hence in 20 days only (1/21 + 2/21) = 3/21 work is completed

To complete the whole work we have to reach the value of (21/21) work.

Now, (1/21) + (2/21) + (3/21) + ......... (6/21) = 21/21 = 1

Hence total time to complete the whole wok 10 + 10 + 10 + 10 + 10 + 10 = 60 days

hope it helps you....

Similar questions