15 men cut a field in 40 days how many days 20 men needs
Answers
Answered by
1
15 men = 40 days
1 men = 15×40 days
20 men = 15×40/20
=30 days
Answered by
1
Men and days to finish the work are in the inverse proportion
so
15*40/20=
30dayes