Math, asked by balwantrai1988, 1 year ago

15 men cut a field in 40 days how many days 20 men needs​

Answers

Answered by abhay2423
1

15 men = 40 days

1 men = 15×40 days

20 men = 15×40/20

=30 days

Answered by maheshv22
1

Men and days to finish the work are in the inverse proportion

so

15*40/20=

30dayes