15 men finish a work in 210 days. But at the end of 100 days 15 additional men are employed then in how many days will work be completed
Answers
Answered by
5
15 * 210 = 3150 total work
100*15 =1500 work done
Remaining = 3150-1500= 1650
And this remaining work is now done by 30 men's
Days = 1650/30 = 55 days
Hope I got it right