15 men take 10 days to complete a job working 12 hours a day how many hours a days should 10 men complete the job in 20 days
Answers
Answered by
0
PLEASE MARK MY ANSWERE AS BRAINLIST
When 10 men are required to complete the same job in 20 days working h hours a day, work done =10×20×h. But 10×20×h=15×10×12. Hence the number of hours for which they should work per day is 15×10×1210×20=9. ∴ 10 men can complete the work in 20 days working for 9 hours per day.
Answered by
0
15×10×12 = 10×20× x
x = 15×10×12 divided by 10 × 20
x = 9 answer