15 men working 10 hours a day take 18 days to do a work, how many hours should 20 men work to finish the same work in 12 days?
Answers
Answered by
2
= 6 hours a day must 15 men work to complete the same work in 12 days. Step-by-step explanation: Given :10 men, working.
Answered by
0
Step-by-step explanation:
15 men finish the work in 10×18 hours
1 man finish the work in 10×18×15 hours
20 men finish the work in 10×18×15/20 hours=135 hours
12 days require to finish the work
then daily work is135/12 hours
=11 3/12 hours
=11hours 15 mins