Math, asked by pusuluriyaswinisai, 8 months ago

15 mens can take to complete 30 days piece of work than the 30 mens can ​

Answers

Answered by jitendrasinghsolanki
0

Answer:

plz share your book plz it is not possible without the book

Answered by avk6418peh6wh
0

Answer:

15 days

Step-by-step explanation:

15 men --- 30 days

30 men --- ? days

No. of days=30/2=15 days

Similar questions