15 person finish a work in 30days .how many person are required to finish the same work in 45days.

Answers

Answered by dipakj22
0
1 person takes 2 days, x people takes 45 days. x=27.5

vaishwikmishra: it is inverse variation
vaishwikmishra: not direct
Answered by vaishwikmishra
0

Answer:

10 persons

Step-by-step explanation:

15 persons finish the work in 30 days

(15 * 30)/45 persons finish the work in 45 days

10 persons finish the work in 45 days