Math, asked by star8879, 1 year ago

15 persons completed a job in 7 days how many days will 10 persons take to complete the job

Answers

Answered by emma18
0
If no. of person decreases no. of days increases

15*7/10=10.5

emma18: Yes?
emma18: Im doing good
Answered by shivchandrapanchal
0

Answer:

10.5 is ur ans

Step-by-step explanation:

M=15 D=7

man—days=15*7=105

hence for same man days for 10 persons

no of days =105/10=10.5 days