Math, asked by SiDD77, 4 months ago

15. Ram, Shyam and Mohan completed a work togelhor for which they got
R. 63.35. Il Ram can complete the work in 2 days, Shyam in 4 days and Mohan in 8 days, then how much money should Shyam get ?

Answers

Answered by Anonymous
0

Answer:

togelhor for which they got

R. 63.35. Il Ram can complete the work in 2 days, Shyam in 4 days and Mohan in 8 days, then how much money should Shyam get ?

Answered by rushikeshphapale4
2

Answer:

R can complete a piece of work in 25 days. In 1 day, R can complete (1/25) of a piece of work.

S can complete a piece of work in 20 days. In 1 day, S can complete (1/20) of a piece of work.

R and S work together for 5 days and complete 5(1/25) + 5(1/20) = (9/20) of a piece of work.

S has to complete (11/20) of the piece of work by himself.

(1/20) of work can be completed in 1 day.

(11/20) of work can be completed in 11 days ie S can complete the piece of work in 11 days.

Step-by-step explanation: