Representation of a project on paper is based on: (a) first-in-first out (b)
work break down structure (c) Pareto's rule (d) Precedence logio
2​

Answers

Answered by dharanikamadasl
0

Answer:

Option b - work breakdown structure is the correct answer.

Explanation:

  • A work breakdown structure (WBS) is a deconstruction of a project that is visible, hierarchical, and focused on deliverables.
  • It's a useful diagram for project managers since it allows them to break down the scope of their projects and visualise all of the tasks needed to finish them.
  • The work breakdown structure chart is a critical project planning tool because it outlines all project work processes.
  • The ultimate project deliverable, as well as the tasks and work packages associated with it, are located at the top of the WBS diagram, whereas the WBS is located at the bottom, while the WBS levels below partition the project scope to represent the activities, deliverables, and work packages required to complete the project from beginning to end.
  • Project managers utilise project management software to create and implement a job breakdown structure.
  • Project management software can be extremely useful for scheduling, executing, and planning projects when combined with a Gantt chart that includes WBS levels and task hierarchies.

Hence, a representation of a project on paper is based on a work breakdown structure.

#SPJ3

Answered by bharathparasad577
0

Answer:

Concept:

work breakdown structure (WBS) is a visible, hierarchical, and deliverable-focused deconstruction of a project.

Explanation:

It's an excellent diagram for project managers because it allows them to break down the scope of their projects and visualize all of the tasks required to complete them.

Because it outlines all project work processes, the work breakdown structure chart is an essential project planning tool.

The ultimate project deliverable, as well as the tasks and work packages associated with it, are at the top of the WBS diagram, while the WBS is at the bottom, and the WBS levels below partition the project scope to represent the activities, deliverables, and work packages required to complete the project from start to finish.

A job breakdown structure is created and implemented by project managers using project management software.

When combined with a Gantt chart that includes WBS levels and task hierarchies, project management software can be extremely useful for scheduling, executing, and planning projects.

As a result, a project's paper representation is based on a work breakdown structure.