15 weavers can weave some length of cloth in 1 hr. 24 minutes. How many more weavers are required to do the same job in 60 minutes?​

Answers

Answered by llItzDeadlyThreatsll
3

Answer:

21 weavers

Step-by-step explanation:

15 weavers = 1hr 24 min

=60min+24min=84min

1 Weaver = 84×15

60 min=84×15/60

=1260/60=21weavers

I hope it helped