15 women finish the work of harvesting a groundnut crop in 8 days. Find the number of women if the same job is to be completed in 6 days.
Answers
Answered by
4
Solution:The number of days required to finish a job is inversely proportional to
the number of women employed. Let the number of days be d and number
of women be n.
d D 1
- n d u n = k (k is constant)
If n = 15, then d = 8 \ k = d u n = 15 u 8 = 120
Now let us find n when d = 8.
d u n = k
- d u n = 120 \ 6 u n = 120, n = 20
- 20 women should be employed to finish the work in 6 days