15 worker can do a piece of work in 15 days then how many days 10 workers will take
Answers
Answered by
1
Answer:
15 workers = 15 days
1 worker = 15 ÷ 15
= 1 day
So,
10 workers =. 1 × 10
= 10 Days
Hope it will help you !!!!