15 workers finish building a wall in 8 days if to be completed in 6 days then the number of workers required is
Answers
Answered by
0
Answer:
i think 15 workers are needed
Answered by
0
Answer:
As number of days de crease, the number of workers increase.
It is in inverse variation
Constant (k)= xy
x -> 15 x
y -> 8 6
6x = 15 x 8
6x = 120
x = 120/6
x = 20
Therefore, 6 men take 20 days to finish the building
Hope this helped you
Mark me as the brainliest