15 workers take 11 days to dig a pond. How many workers should be employed to complete the same work in 3​

Answers

Answered by tappatel230
0

Answer:

33 days

Step-by-step explanation:

One pond = 11 day

11x3

=33 days

Answered by sakshii8080
0

According to the information provided in the question.

It is stated in the preceding question that,

The presented information is 15 workers take in 11 days to dig a pond,

We need to find how many workers should be employed to complete the same work in 3 days​.

As a result, the simplify equation is,

The required number of worker to complete same work be x.

15\times 11=x \times 3

165=3x\\3x=165

x=\frac{165}{3} \\x=55

55 workers should be employed to complete the same work in 3​ days.

Note:-15 workers take 11 days to dig a pond. How many workers should be employed to complete the same work in 3​ days.