15. X number of men can finish a piece of work in 30
days. If there were 6 men more, the work could be
finished in 10 days less. What is the original number
of men?
(a) 10
(b) 11 (c) 12 (d) 15
(e) 13
Answers
Answered by
2
Given:-
If . X number of men can finish a piece of work in 30
days. If there were 6 men more, the work could be
finished in 10 days less.
To Find :-
What is the original number of men?
Solution :-
We may observe that the question is going in indirect proportion
Here,
30 x = 20(6 + x)
30x = 120 + 20x
30x - 20x = 120
10x = 120
x = 120/10
x = 12